What should a line item show the customer?
Source, basis, date, or don't ship the number.
A priced line that cannot say where the figure came from and how old it is will not survive the first customer who asks, and the moment you invent a source to fill the gap the problem stops being yours and becomes theirs.
The four things on a defensible line
Quantity and unit, so they can check it against the plan. Unit price. Where the price basis came from. The date that basis is good as of. A line missing the last two is a number the customer has to take on faith.
Labor belongs on the same footing: the role, the hours, and the loaded rate you actually pay, not a composite from a book.
Say what the number is, exactly
There is a real difference between a written quote from your supplier for this job, and a reference figure that tells you roughly what this item runs in this market. Both are useful. Only one is a commitment from a vendor, and a proposal that blurs them is setting up an argument later.
Portravo prints the source, the location and an as-of date on every priced material line and carries the same columns into the Excel export. Check whether each line uses a retrieved local price or a benchmark fallback, and read any indexed label. These are a basis for your bid, not a quote held open for you, so get supplier confirmation on the big lines before you commit.
Show what an allowance covers
When a finish or fixture is still undecided, label its allowance and record what it covers, the quantity and unit used, the price basis and date, and who makes the selection. Show separately where installation, delivery and tax appear so the customer can tell what is included in the estimate.
Illustrative example: Floor tile material allowance, sheet A2.1, 48 square feet at an assumed $6 per square foot, for $288. Basis: estimator planning allowance, November 8, 2026. Owner selection pending. Installation, delivery and tax are listed separately in this example.
If the selected tile costs $7.50 per square foot on the same quantity and scope, the material line becomes $360, a $72 difference. Record the supplier and quote date and show the revised amount for review. If the selection changes the quantity or installation work, show those changes on their own lines.
What to leave off
Your markup does not need its own line on the customer copy. Neither does your internal contingency reasoning. The customer-facing PDF should be clean; the Excel export is where you keep the full bill of materials with the source and date columns for yourself.
And leave off anything you cannot back up. A fabricated citation on a proposal a homeowner forwards to three other bidders is a worse outcome than having no citation at all.
Line item checklist
Use these checks before sharing a priced line.
- 01Quantity and unit the customer can check against a sheet.
- 02Unit price and extended price.
- 03A named basis for the price: a supplier quote, your own invoice, or a dated benchmark.
- 04The date that basis is good as of.
- 05Labor shown by role and loaded hourly rate, from your rate card.
- 06For an allowance, identify the pending selection, what the allowance covers, and what is priced separately.
- 07Nothing on the line you could not produce a document for if asked.
No account, no card. Send your last supplier quote as a PDF and it comes back marked against the dated Portravo benchmark within one business day.
Send a supplier quote for a free audit- Does Portravo show the customer where each price came from?
- Yes. Every priced material line carries its source, location and an as-of date, and those columns are in the Excel export as well as the customer PDF. They identify the retrieved local price or benchmark fallback used for that line, not a supplier quote held open for you.
- Should I show my markup to the customer?
- That is your call and it varies by market, but the itemized cost detail and your margin are separate decisions. Portravo exports a clean customer PDF and a full Excel bill of materials so you can share one without the other.