Construction estimate review worksheet: verify scope, quantities, and price basis Review a construction takeoff before bidding: trace quantities to plans, confirm units and waste, check dated material prices, and document exclusions. Identify the plan set and scope Use this worksheet before a draft takeoff becomes a priced bid. Start with the drawing revision, included trades, and scope boundaries. A quantity can be accurately counted from the wrong sheet and still be wrong for the job. Store real plans, supplier quotes, customer details, and commercial terms privately. This public worksheet is an educational review aid, not a professional certification of an estimate. Project reference and plan-set revision: ______ Included trades, alternates, and exclusions: ______ Reviewer and unresolved scope questions: ______ Review each quantity For every priced line, retain a sheet or source reference, material specification, unit, measured quantity, waste assumption, and reviewed order quantity. Check that a count, length, area, or volume has not been substituted for another unit. Investigate uncertain or omitted lines before relying on the total. Human confirmation of one line does not validate every assembly in the plan set. Plan sheet and line item: ______ Specification and unit: ______ Measured quantity and measurement method: ______ Waste assumption and rounding rule: ______ Reviewed order quantity and reviewer: ______ Confirm what the price means Separate a dated reference benchmark from a current supplier quote. Record source, as-of time, location, unit, and whether tax, freight, labor, overhead, and contingency are included. Confirm availability and substitutions with the supplier before committing to the job. Portravo uses authored Sacramento material benchmarks and labeled regional adjustments elsewhere. Those are estimating references, not live supplier offers. Bring your own labor-rate basis and review current procurement conditions. Material price source and as-of time: ______ Benchmark or supplier quote: ______ Location and unit-price match: ______ Labor, tax, freight, overhead, and contingency treatment: ______ Supplier confirmation and unresolved items: ______ Reconcile the bid before release Illustrative quantity example: 40 studs plus a chosen 10% waste allowance gives 44 studs. The allowance is an assumption for this example, not a universal rule. Multiply by a confirmed per-stud price, then keep additional cost components visible. Markup and margin use different bases. With an illustrative cost of 100 and a selling price of 125, markup is 25% and gross margin is 20%. Use the same definitions throughout the estimate and avoid counting overhead twice. Arithmetic, units, and duplicated scope checked: ______ Markup versus margin convention: ______ Included costs and exclusions attached: ______ Remaining assumptions communicated: ______ Final reviewer and release decision: ______ Use the worked example Portravo provides a worked material estimate and a free quote-audit entry point. Use them to see the review structure, then validate your own project quantities and supplier basis. This worksheet makes no claim about customer savings, takeoff accuracy, or final bid suitability. Published by Portravo Related guide: https://portravo.com/guides/construction-estimate-review-checklist Product: https://portravo.com/examples/material-estimate